Key Dates and Data Collection Schedule for the 2017 ICH CAHPS Spring Survey
folder_openOther Announcementscalendar_todayPosted November 3, 2016
The tentative data collection schedule and the dates for some key activities related to the 2017 In-Center Hemodialysis CAHPS (ICH CAHPS) Spring Survey are shown below. Please note that these dates are subject to change. Should a schedule change occur, an announcement will be posted. Key dates for the 2017 Fall Survey will be announced later in 2017.
Activity |
Date |
Introduction to the ICH CAHPS Survey Webinar Training |
2/15/2017 |
ICH CAHPS Survey Vendor Update Training Session |
2/16/2017 |
Deadline for Authorizing a Vendor for Spring Survey1 |
5:00 PM, ET, 2/28/2017 |
Submit New Facility-Specific Questions for Approval |
5:00 PM, ET, 1/31/2017 |
Deadline for Registering for the Introduction and the Vendor Update Training Webinar Sessions |
5:00 PM, ET, 2/10/2017 |
Deadline for Submitting the Quality Assurance Plan |
11:59 PM ET, 3/31/2017 |
|
|
Sampling Window |
10/1/2016-12/31/2016 |
Sample Files Uploaded on ICH CAHPS Website |
3/31/2017 |
Vendors Attest to Receipt of Sample File |
4/4/2017 |
Mail Prenotification Letter |
4/21/2017 |
Mail 1st Questionnaire (mail only and mixed mode) /Begin Telephone data collection (phone only mode) |
5/5/2017 |
Mail 2nd Questionnaire to mail only mode nonrespondents/Begin phone follow-up with mixed-mode nonrespondents |
6/2/2017 |
Data Collection Ends |
7/14/2017 |
Vendors clean/process final data and construct XML File |
7/17/2017-7/26/2017 |
Deadline for Submitting XML Data File to ICH CAHPS Data Center |
7/26/2017 |
1 Only ICH facilities that will be switching to a different survey vendor and those that will be participating in the ICH CAHPS Survey for the first time will need to complete the online vendor authorization form.