Activity

Date

Sampling Window

10/1/2015-12/31/2015

Sample Files Uploaded on ICH CAHPS Website

4/1/2016

Vendors Attest to Receipt of Sample File

4/5/2016

Mail Prenotification Letter

4/22/2016

Mail 1st Questionnaire (mail only and mixed mode) /Begin Telephone data collection (phone only mode)

5/6/2016

Mail 2nd Questionnaire to mail only mode nonrespondents/Begin phone follow-up with mixed-mode nonrespondents

6/3/2016

Data Collection Ends

7/15/2016

Vendors clean/process final data and construct XML File

7/16/2016-7/27/2016

Deadline for Submitting XML Data File to ICH CAHPS Data Center

7/27/2016